Running the WIP Report

Once you run the ‘WIP Report - Detailed’, it is necessary to set up the correct filters
and grouping to review the specific details in the format you require.

Available Filters

  • Actuals up to and including - This is a ‘select month’ dropdown. This will
    determine the cut-off month for the ‘Actual’ figures.
  • Status - This is the status of the project. Defaults to ‘Ongoing’ but can select a
    specific project status if required.
  • Branch - Defaults to ‘All’ but can select a specific branch
  • Director - Defaults to ‘All’ but can select a specific Director if required.
  • Manager - Defaults to ‘All’ but can select a specific Manager if required.
  • Discipline - Defaults to ‘All’ but can select a specific Discipline if required.
  • Report Currency - Defaults to systems default currency but can select an alternative currency if required.
  • W/S Probability - Defaults to ‘All’ but can select from the following:
    • Confirmed only
    • Low and above
    • Medium and above
    • High and above
  • W/S Status - Defaults to ‘All’ but can select from the following:
    • Open
    • Closed
    • By Duration
  • Fee Type - This splits the fee by ‘Base’ and Additional’. 
    Defaults to ‘All’ but can split fees by base or additional
  • Inc. Rechargeable Expenses - Yes/No option.
    The report will default to ‘include rechargeable expenses = No’.
    This will affect all columns which can ‘include’ or ‘exclude’ Rechargeable
    expenses.
    Non-Rechargeable expenses are included in calculations.
  • Forecast Mode - Choose between:
    • Using Estimated % Complete – This will affect the forecast costs column and all calculations using this figure.
    • Using Budget Forecast – This will affect the forecast costs column and all calculations using this figure.
  • Toggle Grouping Console - to review the following categories that you can group by:
    • Branch
    • Client
    • Director
    • Parent project
    • Sector
    • Project Status

The report can be split across the following areas:

Project Details

  • Listing of the standard project details to allow you filter and group as follows:
    • Clients (group)
    • Project Currency (auto)
    • Report Currency (select one)
    • Project Status (filter, group)
    • Director (Filter, group)
    • Manager (filter)
    • Branch (Filter, group)
    • Sector (group)
    • Discipline (Filter)

 

Budget Plan

  • This section highlights the original budget entries completed at the beginning of the project. These figures can be seen on the Workstage Tab.
Total FeeThis is the amount entered on the Workstage Tab
Sub Con Budget CostsThis is the amount entered on the Subconsultant Plan. This will change if you select the Inc. rechargeable expenses filter.
Total Budget CostsThe budget costs are calculated by adding the totals on the Labour Plan, Subconsultant Plan and Expenses Plan
Budget P&LCalculation (Total Fee Less Total Budget Cost)
Budget P&L %Calculation

 

Actuals

  • This section shows all the actual invoiced to date less the actual costs.
  • The Actuals are up to and including the month which has been selected in the filter at the top of the report.
  • These figures can be seen on the Performance Summaries Tab.
Fee issued to dateInvoicing to date
Subcon cost to dateNon- rechargeable projects expenses booked against subconsultants nominal code
Cost to DateTimesheets & Non-rechargeable Costs to date
P&L to DateCalculation
P&L to Date %Calculation
  • The report defaults to ‘include rechargeable expenses = No’.
  • The filter should be changed if you would like to see recoverable expenses included in the calculations.

 

Anticipated Final Position

  • This section forecasts the anticipated profit of the project.

Anticipated Final Fee

Anticipated Subcon Costs

Higher of ‘Total Fee’ or ‘Fees invoiced to date + forecast billing plan’
projects expenses booked against subconsultants nominal code + forecast subconsultants

*Anticipated Final Costs

Anticipated profit

Costs Costs to date + forecast costs
Calculation
Anticipated P&L %Calculation

Forecast Mode

This Anticipated Final Cost column is calculated using the Forecast mode selected.

The Forecast Mode can be explained as follows:

  • Budget Costs: The final cost is calculated based on the all actual costs to date, plus remaining forecast in the Labour Plan, Subconsultant Plan and Expenses Plan.
  • Estimated % Complete: The final cost is calculated based on the estimated % complete as follows:
Labour CostEst % Complete
21,09465%
32,452100%
  • If the project cost £21,094 to reach 65% complete, based on the work being carried out in a consistent approach, it will take £32,452 to reach 100% complete.

Calculation:

21,094 x 100%
65%
=£32,452
  • For a project with multiple Workstage, a weighted average estimated % complete is calculated for the project as a whole as follows:
 Total FeeEst % completeFees EarnedWeighted Est % Complete
Stage 112,250100%12,250 
Stage 217,50060%10,500 
Stage 35,2500%- 
TOTAL PROJECT35,000 22,75065%
Calculation:22,750 x 100
35,000
=65%

 

% Complete Comparisons

Fee % issuedCalculation:
(Fees to date/Anticipated Final Fee) x 100
Cost % CompleteCalculation:
(Cost to date/Anticipated Final Cost) x 100
Est % CompleteWeighted Average WIP as calculated above

 

Project Additional Information

Parent project

Fees Earned to Date (based on cost % Complete)

Parent project Parent project of the project
Calculation: Anticipated Final Fee x cost % complete
Fees Earned to Date (based on Est % Complete)Calculation: Anticipated Final Fee x est % complete
Last Cost Entry DateDate - from timesheet/expenses
Last Invoice DateDate - from invoicing
Costs since last invoiceTimesheets & Costs since last invoice date

Cost since year end
Cost in previous month

Subconsultant Accrual

Timesheets & Costs since year end
Timesheets & Costs since previous month end
Calculation: Subconsultants invoiced to client to date (nominal codes) less Subconsultants invoices received from subconsultant to date (project expenses)

 

Amounts Recoverable on Contract

Basic WIP

If project has invoiced, Basic WIP is N/A.

If project has not yet invoiced, Basic WIP is calculated as costs to date

AROC using Labour Cost % Complete of Fees Earned

Calculation: If project has invoiced, AROC calculated as fees earned less fees issued.

If project has not yet invoiced, AROC calculated as cost to date

AROC using Est % Complete of Fees Earned

Calculation: If project has invoiced, AROC calculated as fees earned less fees issued.

If project has not yet invoiced, AROC calculated as cost to date